ACOE's permit reviewer Peter Tischbein has approved the sampling and analysis plan by Nordic AquaFarms for Nordic to test sediments while digging and dredging to dig and dredge a subsurface pipeline route to let the company discharge wastewater from its upland-based fishfarm into Belfast Bay, On June 18, 2020 he released the following document - but not to any interested party but NAF!
* FINAL Sampling and Analysis Plan for the Nordic Aquafarms Pipeline CorridorDredging, Belfast and Northport, ME, 20 pg PDF June 22, 2020 Cover letter to Nordic consultant Elizabeth Ransom
Paul Bernaki licenced longtime wetlands, uplands and and intertidal and subtidal lands consultant (with insertions by Attorny Kim Tucker)